go home

Select a Professional Development Module:
Key Topics Strategy Scenario Case Study References

Introduction |  Step 1 |  Step 2 |  Step 3 |  Step 4 |  Step 5 |  Step 6 |  Step 7 |  Step 8 |  Step 9

Step 4. Periodically monitor all aspects of data collection.

As project leader, you have established biweekly meetings with those responsible for data collection. Key individuals report the status of their work. In one of the meetings, your review of various schedules revealed a conflict between the school schedule and a scheduled site visit. This difference in schedule was not identified in previous phone conversations with school staff. An alternative date was found that accommodated both the data collectors and teachers.